Date:April 23, 2010
For Wastewater Treatment Unit of Inner Mongolia Datang International Keshiketeng 12,000,000 Nm3 /d Coal-to-Natural Gas Project, China National Water Resources & Electric Power Materials & Equipment Co., Ltd (CWEME)for and on behalf of Datang Energy Chemical Co., Ltd. (DEC) invites eligible technique suppliers for request for technical scheme openly and internationally, and publishes the Announcement at website of Chinabidding on April 23, 2010.
A、Project Profile:
Datang Energy Chemical Co., Ltd. (DEC) is wholly owned by Datang International Power Generation Co., Ltd, which is listed company in London, Hong Kong and Shanghai. DEC’s central business is to develop the energy chemical industry and other related industry under the leadership of China Datang Corporation. Inner Mongolia Datang International Keshiketeng Coal-to-Natural Gas Project, was the first one approved by National Development and Reform Commission, and is now under construction.
The designing production capacity of the project is 4 billion Nm3 natural gas
, and the project is built by three stages, which uses lignite as raw material. The project utilizes some technologies to produce natural gas and other related by-products, such as Smashed Coal Pressure Gasification, Sulfur Tolerant Shift, Rectisol Process, Methanation and so on. The project will discharge average 1945 m3/h wastewater, including coal-gasification wastewater, methanol process wastewater, domestic wastewater, floor washing wastewater. The wastewater should be treated in Wastewater Treatment Unit. Part of qualified treated wastewater is used as make-up water in Circulating Water System, the other is used as raw water in Desalting Water System in power workshop.Concentrated saltwater and secondary wastewater produced in Wastewater Treatment Unit should be collected and treated by sort. The recovery measures and related treatment process must be designed.
B、Project name:
Request for technical scheme of Wastewater Treatment Unit of Inner Mongolia Datang International Keshiketeng 12,000,000 Nm3 /d Coal-to-Natural Gas Project.
C、Purpose of request for technical scheme:
For technical scheme of Wastewater Treatment Unit of Inner Mongolia Datang International Keshiketeng 12,000,000 Nm3 /d Coal-to-Natural Gas Project, DEC will clarify a scientific, perfect and pertinent technical scheme. It is not an official bidding, and only technique preparation before Bidding.
D、Registration Requirements:
1、Registration Date: from 08:30 to 11:30 am, from 13:30 to 16:30 pm(Beijing time), except holidays, from April 23, 2010 to May 31, 2010
2、Registration Place: Room C608 Dian’yan Building No. 1 Dizang’an Nanxiang,Fuxingmenwai,Xicheng District, 100045 Beijing, P.R. China
3、Registration:fax or come to the Place with documents
4、Documents for registration at place:
Business License(copy of original document),
Qualification Documents(copy of original document)
5、Documents for registration by fax:
technique supplier name、contact person、telephone、fax、Business License(copy of original document), Qualification Documents(copy of original document)
E、Submitting time、place、content and requirements of technical scheme:
1、Deadline for submitting: 17:00 pm May 31, 2010. Delayed documents will not be accepted.
2、Place for submitting:Room C608 Dian’yan Building No. 1 Dizang’an Nanxiang,Fuxingmenwai,Xicheng District, 100045 Beijing, P.R. China
3、Documents to be submitted:
1)Business License(copy with official seal)、Qualification Documents(including:ISO9000 and ISO14001 certificate),in two copies.
2)Content and requirements of technical scheme:For wastewater treatment plant of Inner Mongolia Datang International Keshiketeng 12,000,000 Nm3 /d Coal-to-Natural Gas Project, each technique supplier should provide the technical scheme based on its own technology and the requirements of Technical Scheme Proposal.
The technical scheme should be provided with Chinese version or Chinese-English version. All documents should be provided together with one (1) complete electronic copy with Chinese version or Chinese-English version in CD-ROM or flash-disk.
4、How to get Technical Scheme Proposal:
Contact with CWEME after registration.
5、Technical exchange: contact with CWEME if needed.
F、Price of Technical Scheme Proposal:FREE
G、Contact:Mrs Sun Xuelian, Mr.Li Weizhong
China National Water Resources & Electric Power Materials & Equipment Co., Ltd
Address:Room C608 Dian’yan Building No. 1 Dizang’an Nanxiang,Fuxingmenwai,Xicheng District, 100045 Beijing, P.R. China
Tel:010-51967916,51967867
Fax:010-51967918,51967864
China National Water Resources & Electric Power Materials & Equipment Co., Ltd
April 23, 2010
|